Highway 1 Bridge Replacement Eastbound at Kilometre 1.16

Chaplin, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$560,700
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Aug 9, 2010(actual)
Construction end
Dec 2, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2010
  • Construction end4 weeks earlyforecast Dec 31, 2010