Highway 1 Bridge Replacement Eastbound at Kilometre 2.3
Federal contribution
$523,700
Federal share50%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Dec 2, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2010
- Construction end4 weeks lateforecast Nov 1, 2010
Also in Chaplin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33276 in the federal list. How to read these figures.