Highway 1 Bridge Replacement Eastbound at Kilometre 1.77
Federal contribution
$776,500
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Dec 2, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2010
- Construction end4 weeks earlyforecast Dec 31, 2010