Rehabilitation and Renewal of the Chaplin Family YMCA
Federal contribution
$341,681
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- YMCA of Cambridge
- Construction start
- May 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 15, 2009