Highway 1 East of Herbert to Rush Lake

Herbert, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$1.7M
$1,692,079
Federal share50%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Aug 30, 2009(actual)
Construction end
Sep 30, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2009
  • Construction end6 months earlyforecast Mar 31, 2010