Town of Herbert - Herbert Landfill Closure

Herbert, Saskatchewan

underwaySolid Waste ManagementGIS
Federal contribution
$280,307
Federal share40%

of $700.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
2023202420252026
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Herbert
Construction start
Oct 27, 2025(actual)
Construction end
Mar 31, 2026(forecast)