New Wastewater Pump Stations
Federal contribution
$362,288
Federal share50%
of $724.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Herbert
- Construction start
- Aug 20, 2018(actual)
- Construction end
- Jun 19, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 16, 2018
Also in Herbert