New Wastewater Pump Stations

Herbert, Saskatchewan

completeWastewaterCWWF
Federal contribution
$362,288
Federal share50%

of $724.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Herbert
Construction start
Aug 20, 2018(actual)
Construction end
Jun 19, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 16, 2018

Also in Herbert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50040 in the federal list. How to read these figures.