Back to projects

South River Community Beautification

Parry Sound, Ontario

completeTourismG8LF
Federal contribution
$64,276
Federal share100%

of $64.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 15, 2009
ApprovedNov 10, 2009
2010
Built

Approved 5 months after the announcement.

Program
G8 Legacy Fund
Construction start
Jun 1, 2009(actual)
Construction end
Jun 1, 2010(actual)

Also in Parry Sound

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33364 in the federal list. How to read these figures.