Road Construction - Grading on Project No. 458, Class 5 Municipal Road

Clayton No. 333, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$70,998
Federal share33%

of $213.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built

Approved 8 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Aug 3, 2009(actual)
Construction end
Dec 22, 2009(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 11, 2009

Also in Clayton No. 333

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33396 in the federal list. How to read these figures.