Rural Municipality of Clayton No. 333, Dyck Memorial Road Bridge Replacement
Federal contribution
$166,650
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Clayton No.333
- Construction start
- Apr 15, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start15 months lateforecast Jan 15, 2020
- Construction end6 months lateforecast Dec 31, 2021
Also in Clayton No. 333
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57331 in the federal list. How to read these figures.