Road Construction - Grading on Project No. 454, Class 5 Municipal Road
Federal contribution
$142,233
Federal share33%
of $426.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 26, 2009
ApprovedJan 27, 2010
2010
Built
Approved 8 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Dec 22, 2009(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 11, 2009
Also in Clayton No. 333
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33399 in the federal list. How to read these figures.