Childrens Aid Society - Phase 2
Federal contribution
$836,667
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Children's Aid Society of the Niagara Region
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Jul 5, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 21, 2010
- Construction end6 weeks lateforecast May 27, 2011
Also in Niagara Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33849 in the federal list. How to read these figures.