Building Upgrades/Efficiency Upgrades - Big Brothers Big Sisters of Hamilton and Burlington facility

Hamilton, Ontario

completeRecreationISF
Federal contribution
$235,449
Federal share19%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Dec 24, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Nov 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011