Building Upgrades/Efficiency Upgrades - Big Brothers Big Sisters of Hamilton and Burlington facility
Federal contribution
$235,449
Federal share19%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Big Brothers Big Sisters of Hamilton and Burlington
- Construction start
- Dec 24, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Nov 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34020 in the federal list. How to read these figures.