New YMCA Facility in Fredericton

Fredericton, New Brunswick

completeRecreationISF
Federal contribution
$5.3M
$5,275,000
Federal share33%

of $15.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2009
20102011
Built

Approved 7 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Fredericton YMCA
Construction start
Feb 26, 2010(actual)
Construction end
Oct 3, 2011(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Aug 31, 2011