Antoine Beaulieu Community Hall
Fort Resolution, Northwest Territories
Federal contribution
$250,000
Federal share50%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 11, 2009
20102011
Built
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Community of Fort Resolution
- Construction start
- Nov 23, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 30, 2010
- Construction end2 months earlyforecast Oct 31, 2011