Sewage Lagoon
Fort Resolution, Northwest Territories
Federal contribution
$1.9M
$1,917,000
Federal share75%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Hamlet of Fort Resolution
- Construction start
- Feb 1, 2017(actual)
- Construction end
- Mar 13, 2020(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Mar 31, 2020
Also in Fort Resolution