Back to projects

Youth Centre and Pool Improvements

Fort Resolution, Northwest Territories

completeRecreationSCF
Federal contribution
$125,000
Federal share75%

of $166.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 4, 2020
202020212022202320242025
Built

Approved 17 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Hamlet of Fort Resolution
Construction start
Jul 2, 2021(actual)
Construction end
Jan 8, 2025(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 15, 2021
  • Construction end16 months lateforecast Aug 31, 2023

Also in Fort Resolution

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54363 in the federal list. How to read these figures.