Bridge Replacement on Ashnola Forest Service Road
Federal contribution
$67,000
Federal share48%
of $140.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 1, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 18, 2010
- Construction end3 weeks lateforecast Sep 21, 2010