Village of Keremeos Water System Upgrades
Federal contribution
$788,050
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Keremeos
- Construction start
- Jan 2, 2018(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Mar 1, 2018
- Construction end7 months lateforecast Sep 1, 2018