Keremeos - Critical Inflow and Infiltration Removal
Federal contribution
$155,661
Federal share40%
of $389.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 7, 2023
2024
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Keremeos
- Construction start
- Apr 29, 2024(actual)
- Construction end
- Aug 31, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 1, 2024
- Construction end3 months earlyforecast Dec 15, 2024