Highway 3A Resurfacing
Federal contribution
$899,673
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Apr 21, 2010(actual)
- Construction end
- May 17, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Sep 30, 2010
Also in Keremeos
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 37345 in the federal list. How to read these figures.