Route 10 - Research Station to Little River
Federal contribution
$1.7M
$1,741,000
Federal share50%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Jul 27, 2009(actual)
- Construction end
- Oct 29, 2009(actual)
Also in Fredericton
- University of New Brunswick - Justice Building Renewal$24.9M
- Awitgati Longhouse & Cultural Centre$18.6M
- New Brunswick Broadband$16.5M
- Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal$12.6M
- Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton$11.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34860 in the federal list. How to read these figures.