North Main Community Business Complex

Winnipeg, Manitoba

completeOtherISF
Federal contribution
$1.3M
$1,318,333
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 29, 2009
2010201120122013
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Neechi Foods Co-op
Construction start
Aug 23, 2009(actual)
Construction end
Mar 19, 2013(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jan 1, 2010
  • Construction end3 weeks lateforecast Mar 1, 2013

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34874 in the federal list. How to read these figures.