Route 17 - Whites Brook to Kedgwick Village
Federal contribution
$1.9M
$1,863,500
Federal share50%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- May 24, 2010(actual)
- Construction end
- Jul 30, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 31, 2010
- Construction end7 weeks earlyforecast Sep 18, 2010
Also in Kedgwick
- Kedgwick - Replacement of water and sewer infrastructure - Rue Notre-Dame$1.6M
- Rehabilitation, Infrastructure Update of St. Thomas, St. Jean Baptiste and des Peupliers Streets$697.2K
- Installation of Water Tank to Better Meet Demand$589.2K
- Pipe Replacement and Separation Work - St-Joseph Street$222.8K
- White's Brook Bridge$70.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34915 in the federal list. How to read these figures.