Pipe Replacement and Separation Work - St-Joseph Street

Kedgwick, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$222,840
Federal share50%

of $445.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Kedgwick
Construction start
Apr 3, 2017(actual)
Construction end
Oct 31, 2017(actual)