Kedgwick - Replacement of water and sewer infrastructure - Rue Notre-Dame
Federal contribution
$1.6M
$1,581,925
Federal share40%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2022
202320242025
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Kedgwick
- Construction start
- May 15, 2023(actual)
- Construction end
- Mar 28, 2025(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 15, 2023
- Construction end3 months lateforecast Dec 31, 2024