Repaving of Route 8

Fredericton, New Brunswick

completeHighways and RoadsISF
Federal contribution
$705,434
Federal share46%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
May 25, 2010(actual)
Construction end
Jul 9, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jul 31, 2010
  • Construction end2 months earlyforecast Sep 18, 2010

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34947 in the federal list. How to read these figures.