Western Manitoba Centennial Auditorium
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 29, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Western Manitoba Centennial Auditorium
- Construction start
- Sep 30, 2009(actual)
- Construction end
- Dec 21, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 15, 2009
- Construction end3 weeks lateforecast Nov 30, 2010
Also in Brandon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35050 in the federal list. How to read these figures.