Road Reconstruction

Tahsis, British Columbia

completeHighways and RoadsISF
Federal contribution
$147,017
Federal share28%

of $528.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Tahsis
Construction start
Sep 18, 2009(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Aug 1, 2009
  • Construction end5 months earlyforecast Mar 31, 2011