Road Reconstruction
Federal contribution
$147,017
Federal share28%
of $528.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Tahsis
- Construction start
- Sep 18, 2009(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 1, 2009
- Construction end5 months earlyforecast Mar 31, 2011
Also in Tahsis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35227 in the federal list. How to read these figures.