Tahsis Wastewater Treatment Reconfiguration and Upgrade

Tahsis, British Columbia

completeWastewaterGIS
Federal contribution
$714,000
Federal share40%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2023
202320242025
Built

Approved 11 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Tahsis
Construction start
Aug 1, 2023(actual)
Construction end
Sep 29, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 14, 2023
  • Construction end9 months lateforecast Jan 3, 2025