Tahsis Wastewater Treatment Reconfiguration and Upgrade
Federal contribution
$714,000
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2023
202320242025
Built
Approved 11 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Tahsis
- Construction start
- Aug 1, 2023(actual)
- Construction end
- Sep 29, 2025(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 14, 2023
- Construction end9 months lateforecast Jan 3, 2025
Also in Tahsis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63423 in the federal list. How to read these figures.