Community Water Conservation

Tahsis, British Columbia

completeDrinking WaterCWWF
Federal contribution
$204,451
Federal share50%

of $408.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Tahsis
Construction start
Aug 17, 2017(actual)
Construction end
Mar 14, 2019(actual)

Against the original forecast

  • Construction start15 months earlyforecast Nov 13, 2018
  • Construction end2 weeks earlyforecast Mar 29, 2019

Also in Tahsis

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49845 in the federal list. How to read these figures.