Kawkawa Lake and Memorial Park - Upgrades
Federal contribution
$83,745
Federal share33%
of $251.2K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Hope
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Dec 10, 2010(actual)