Victoria Street Trunk

Fredericton, New Brunswick

completeWastewaterISF
Federal contribution
$364,097
Federal share26%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 12, 2010
2010
Built

Approved 4 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Fredericton
Construction start
Jun 23, 2010(actual)
Construction end
Sep 21, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2010
  • Construction end3 weeks lateforecast Aug 30, 2010

Also in Fredericton