Northwest Drive Path
Federal contribution
$16,325
Federal share33%
of $49.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Masset
- Construction start
- Aug 3, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2010
- Construction end3 months earlyforecast Mar 31, 2011