Masset - Water Treatment Plant Upgrades

Masset, British Columbia

completeDrinking WaterRNIS
Federal contribution
$744,900
Federal share60%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Village of Masset
Construction start
Sep 9, 2022(actual)
Construction end
Mar 15, 2024(actual)

Against the original forecast

  • Construction start9 months lateforecast Dec 15, 2021
  • Construction end2 months lateforecast Dec 31, 2023