Masset Water Main Replacement
Federal contribution
$495,609
Federal share50%
of $991.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Masset
- Construction start
- Jun 7, 2017(actual)
- Construction end
- Oct 12, 2018(actual)
Against the original forecast
- Construction start4 months earlyforecast Oct 10, 2017
- Construction end3 months lateforecast Jul 16, 2018