Masset Water Main Replacement

Masset, British Columbia

completeDrinking WaterCWWF
Federal contribution
$495,609
Federal share50%

of $991.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Masset
Construction start
Jun 7, 2017(actual)
Construction end
Oct 12, 2018(actual)

Against the original forecast

  • Construction start4 months earlyforecast Oct 10, 2017
  • Construction end3 months lateforecast Jul 16, 2018

Also in Masset

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49835 in the federal list. How to read these figures.