Back to projects

O’Siem Community Pavilion

Squamish, British Columbia

completeRecreationISF
Federal contribution
$166,667
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Squamish
Construction start
Mar 14, 2011(actual)
Construction end
Oct 25, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Feb 21, 2011
  • Construction end4 months lateforecast Jun 25, 2011