OSiem Community Pavilion
Federal contribution
$166,667
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Squamish
- Construction start
- Mar 14, 2011(actual)
- Construction end
- Oct 25, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Feb 21, 2011
- Construction end4 months lateforecast Jun 25, 2011
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35450 in the federal list. How to read these figures.