Back to projects

Princeton Regional Library

Princeton, British Columbia

completeCultureISF
Federal contribution
$199,499
Federal share33%

of $598.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Princeton
Construction start
Dec 29, 2009(actual)
Construction end
Aug 19, 2010(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 1, 2009
  • Construction end2 months lateforecast Jun 15, 2010