Princeton Regional Library
Federal contribution
$199,499
Federal share33%
of $598.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Princeton
- Construction start
- Dec 29, 2009(actual)
- Construction end
- Aug 19, 2010(actual)
Against the original forecast
- Construction start9 months lateforecast Apr 1, 2009
- Construction end2 months lateforecast Jun 15, 2010
Also in Princeton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35466 in the federal list. How to read these figures.