Downtown Revitalization
Federal contribution
$200,000
Federal share26%
of $766.2K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Duncan
- Construction start
- Jul 2, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction end3 months lateforecast Mar 31, 2010
Also in Duncan
- Duncan - Cowichan Valley Flood Protection (Phase 1)$2.6M
- North Cowichan & Duncan Dikes and Pump Station - Phase 3$2.2M
- Duncan - Historic Kinsol Trestle Rehabilitation$1.9M
- Canada Avenue Active Transportation Facilities - City of Duncan / Municipality of North Cowichan$1.9M
- Duncan - Koksilah Industrial Area Dike Construction$1.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35473 in the federal list. How to read these figures.