Wastewater Lagoon System Upgrading
Federal contribution
$166,667
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Cumberland
- Construction start
- Jan 20, 2011(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jan 1, 2011
- Construction end4 weeks lateforecast Jun 1, 2011
Also in Cumberland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35479 in the federal list. How to read these figures.