Cumberland High Performance Wastewater Lagoon Upgrade
Federal contribution
$3.9M
$3,880,000
Federal share40%
of $9.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
2020202220242026
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Cumberland
- Construction start
- Sep 19, 2022(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start2 months earlyforecast Dec 1, 2022
Also in Cumberland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54104 in the federal list. How to read these figures.