Dunsmuir Area I & I Reduction

Cumberland, British Columbia

completeWastewaterSCF
Federal contribution
$922,521
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2015
20162017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Cumberland
Construction start
Jun 13, 2016(actual)
Construction end
May 31, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 23, 2016
  • Construction end2 months lateforecast Mar 31, 2017

Also in Cumberland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46143 in the federal list. How to read these figures.