Dunsmuir Area I & I Reduction
Federal contribution
$922,521
Federal share33%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2015
20162017
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Cumberland
- Construction start
- Jun 13, 2016(actual)
- Construction end
- May 31, 2017(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 23, 2016
- Construction end2 months lateforecast Mar 31, 2017
Also in Cumberland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46143 in the federal list. How to read these figures.