Victoria Road Sewer Rehabilitation
Federal contribution
$142,691
Federal share32%
of $440.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- May 17, 2010(actual)
- Construction end
- Sep 17, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 31, 2010
- Construction end3 months earlyforecast Dec 31, 2010
Also in Sydney
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35493 in the federal list. How to read these figures.