Ashby Road Watermains and Sewers
Federal contribution
$455,000
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Oct 14, 2009(actual)
- Construction end
- Jun 25, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 21, 2009
- Construction end3 months earlyforecast Sep 30, 2010
Also in Sydney
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35538 in the federal list. How to read these figures.