Broadway Street Watermain and Sewer Replacement
Federal contribution
$295,333
Federal share33%
of $886.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- May 17, 2010(actual)
- Construction end
- Nov 19, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 31, 2010
- Construction end6 weeks earlyforecast Dec 31, 2010
Also in Sydney