Watermain Upgrades

Valemount, British Columbia

completeDrinking WaterISF
Federal contribution
$87,267
Federal share33%

of $261.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Valemount
Construction start
Jul 1, 2009(actual)
Construction end
Oct 30, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 2, 2009
  • Construction end3 months lateforecast Aug 1, 2009