Fifth Avenue Lift Station Replacement
Federal contribution
$231,581
Federal share33%
of $694.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 2, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Valemount
- Construction start
- Nov 24, 2016(actual)
- Construction end
- Aug 31, 2017(actual)
Against the original forecast
- Construction start4 months earlyforecast Apr 1, 2017
Also in Valemount
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46164 in the federal list. How to read these figures.