Back to projects

Sewer Lift Station Enhancements

Valemount, British Columbia

completeWastewaterISF
Federal contribution
$55,000
Federal share33%

of $165.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Valemount
Construction start
Oct 6, 2010(actual)
Construction end
Aug 26, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 1, 2010
  • Construction end8 weeks lateforecast Jun 30, 2011

Also in Valemount

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36765 in the federal list. How to read these figures.