Sewer Lift Station Enhancements
Federal contribution
$55,000
Federal share33%
of $165.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Valemount
- Construction start
- Oct 6, 2010(actual)
- Construction end
- Aug 26, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 1, 2010
- Construction end8 weeks lateforecast Jun 30, 2011
Also in Valemount
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36765 in the federal list. How to read these figures.