Port Hardy Curling Club Retrofit

Port Hardy, British Columbia

completeGreen EnergyISF
Federal contribution
$64,667
Federal share33%

of $194.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Port Hardy
Construction start
May 13, 2009(actual)
Construction end
Feb 10, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2009
  • Construction end4 months lateforecast Sep 30, 2009