Sewage Lagoon Upgrades

Osoyoos, British Columbia

completeWastewaterISF
Federal contribution
$134,333
Federal share33%

of $403.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
2010
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Osoyoos
Construction start
Jun 15, 2009(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jul 1, 2009
  • Construction end7 weeks lateforecast Sep 15, 2010

Also in Osoyoos

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35523 in the federal list. How to read these figures.